Asta PowerProject Password protection

2 replies [Last post]
Lawrence Hooker
User offline. Last seen 2 weeks 2 days ago. Offline
Joined: 18 Dec 2015
Posts: 2
Groups: None

Somehow my PowerProject file has a password set.

I DO know the password but I don't want to have one on it. How do I remove the password?

I can't see any option on any of the task ribbons and nothing in the file properties dialogue...?

Replies

Ben Taunt
User offline. Last seen 1 day 10 hours ago. Offline
Joined: 16 Jan 2012
Posts: 107
Groups: None

7607
pp_password.jpg

Alexandre Faulx-B...
User offline. Last seen 3 days 4 hours ago. Offline
Joined: 20 Jan 2003
Posts: 1336

Hello Lawrence,

Go to File, Password

from Powerproject 15.0 help pages:

https://help.elecosoft.com/powerproject/english/15.0.01/Content/HTML_Top...

Have a good day

Alexandre