P6 Using Baseline with Cost Performance Index - Labor Units

1 reply [Last post]
AMY ALLRED
User offline. Last seen 10 hours 44 min ago. Offline
Joined: 15 Jan 2021
Posts: 8
Groups: None

Hello,

I have created a P6 layout that shows BL1 Start and Finish Dates, BL2 Start and Fiish Dates, Actual Start and Finish Dates and the MHPI (Cost Performance Index - Labor Units). The problem I am having is that I want the MHPI to be based upon the current project schedule as they change every week. What is the best way to do this?

 

Thanks,

AA

Replies

AMY ALLRED
User offline. Last seen 10 hours 44 min ago. Offline
Joined: 15 Jan 2021
Posts: 8
Groups: None

Thanks!

AMY ALLRED
User offline. Last seen 10 hours 44 min ago. Offline
Joined: 15 Jan 2021
Posts: 8
Groups: None

Thanks!

David Kelly
User offline. Last seen 1 week 2 days ago. Offline
Joined: 19 Oct 2004
Posts: 611

Change the “Baseline for Earned Value Calculations” in the Settings Tab in the Projects Window, to the alias that points to the current project.