Variance - BL1 Start Date and Variance - BL1 Finish Date

1 reply [Last post]
AMY ALLRED
User offline. Last seen 10 hours 44 min ago. Offline
Joined: 15 Jan 2021
Posts: 8
Groups: None

Can someone please tell me exactly how the Variance Start and Finish Date columns work? This is what it looks like to me. Am I right?

 

Variance – BL1 Start Date

Variance – BL1 Finish Date

Activity Not Started

BL1 Start – Planned Start

BL1 Finish – Planned Finish

Activity In Progress

BL1 Start – Actual Start

BL1 Finish – Remaining Early Finish

Activity Complete

BL1 Start – Actual Start

BL1 Finish – Actual Finish

 

NOTES

  • If no baseline is attached, BL1 Start and Finish Dates will equal Planned Start and Finish Dates
  • Calendar type affects calculations (example 5 or 6 day work week are used)
  • If an activity is on the current schedule but not the baseline, then the variance columns will be blank for that activity.

Replies

Santosh Bhat
User offline. Last seen 1 day 17 hours ago. Offline
Joined: 15 Apr 2005
Posts: 314

Just be mindful that BL1 is the User's primary baseline, not the Project Baseline. For that you need to use the "BL Project" values.